If you’ve ever watched a rigging team hoist a heavy piece of industrial equipment, a construction steel beam, or a prefabricated building component, you’ve probably noticed how much care they put into positioning the lifting points. One small miscalculation in how load is distributed to those points can turn a routine lift into a dangerous, costly mistake. As someone who’s spent the last 12 years designing, testing, and supplying lifting points for everything from wind turbine nacelles to industrial machinery, I can tell you this: most riggers don’t underestimate the importance of moment calculation for lifting points—but many do underestimate how simple and critical that calculation actually is. Today, I’m breaking down exactly how to calculate moment on a lifting point, why it matters for safety, and how our team’s on-site support for customers makes this process way less stressful. Lifting Point

First, let’s get one thing straight: a lifting point isn’t just a bolt or a hook welded to a piece of steel. It’s a engineered attachment point that’s designed to transfer the load of your lift to your crane, hoist, or rigging equipment. Every lifting point has a load limit, but that limit doesn’t just come from the weight of the object you’re lifting. It also comes from the moment acting on that point—and that’s where most problems start. Moment, in basic terms, is the force that causes rotation around a point. For lifting, that rotation usually happens when the load isn’t perfectly balanced. If your lifting points aren’t positioned so that the center of gravity (CoG) of the load lines up correctly with the plane of the lifting points, you create a side load (that’s a moment) on the lifting point, not just a straight vertical load. That side load is what can cause a lifting point to fail unexpectedly, even if it’s rated for the total weight of the load.
Let’s walk through a real example, because I’ve seen this exact scenario go sideways more times than I can count. Last year, we worked with a structural steel erector who was lifting a 12,000-pound steel beam for a new warehouse. They positioned two lifting points 8 feet apart on the top flange of the beam. They calculated the total weight as 12,000 pounds, so they assumed each lifting point would carry 6,000 pounds. That made sense—until the beam started to lift. The beam twisted 2 inches in the air, and the left lifting point (which had a side load of almost 3,000 pounds) bent slightly. We got a call at our shop that same afternoon, and when we ran the numbers later, it turned out the CoG of the beam was 18 inches to the right of the midpoint between the two lifting points. That meant the load on each point wasn’t 6,000 pounds—it was 7,350 pounds on the right point and 4,650 pounds on the left. Worse, the offset CoG created a moment on each lifting point: the left point had a moment of 450 foot-pounds, and the right point had a moment of 1,260 foot-pounds. The lifting points they’d used were rated for 8,000 pounds vertical load, but their side load rating (which accounts for moment) was only 1,000 pounds total. That’s why the left point bent—its side load from the moment added up to more than its rated limit.
So how do you actually calculate that moment? Let’s make this step-by-step, using that same steel beam example, no fancy engineering degree required. The first thing you need to do is find two key numbers: the total load of your object (W) and the offset distance (d) between the center of gravity (CoG) of your object and the vertical line passing through the lifting point’s position. Moment is calculated as Load multiplied by Distance, right? For lifting, we talk about moment on a per-lifting-point basis, but the base formula is M = F × D, where M is moment, F is the force acting on the object, and D is the perpendicular distance from the point of rotation to that force.
Wait, let’s simplify that for lifting. Let’s stick to the two-point lift example because it’s the most common. First, find the CoG of your load. For a uniform object like that steel beam, the CoG is dead center, 6 feet from each end (if it’s 12 feet long). But if your load is irregular—like a large motor with a heavy gearbox on one end—you’ll need to calculate the CoG. How? You can do this by weighing the object on two separate scales at two points, then use the formula: CoG distance from Point A = (Weight at Point B × Total Length) / Total Weight. That’s a trick we teach every new rigging customer, and it works every time for irregular loads.
Once you have the CoG, measure how far it is horizontally from each lifting point. Let’s go back to that steel beam: total length 12 feet, CoG at 6 feet from the left end. The left lifting point is at 2 feet from the left end, and the right lifting point is at 10 feet from the left end. So the CoG is 4 feet to the right of the left lifting point, and 4 feet to the left of the right lifting point? Wait no, earlier I said the CoG was 18 inches (1.5 feet) to the right of midpoint, so CoG is at 7.5 feet from left end. That makes it 5.5 feet from the left lifting point (7.5 – 2) and 2.5 feet from the right lifting point (10 – 7.5). Now, calculate the vertical load on each lifting point first: Left Load (L_L) = (Total W × Distance from CoG to Right Point) / Total Distance Between Points. Right Load (L_R) = (Total W × Distance from CoG to Left Point) / Total Distance Between Points. For our example, Total W is 12,000 pounds, Total Distance Between Points is 8 feet. L_L = (12,000 × 2.5) / 8 = 3,750 pounds. L_R = (12,000 × 5.5) / 8 = 8,250 pounds. That’s different from the 6,000 pounds they guessed earlier.
Now, the moment comes in if the load isn’t perfectly level when suspended. Wait, no—even if it’s almost level, if the CoG is offset, when you lift, the load will tilt slightly, and that tilt creates a horizontal force on the lifting point, which is the moment. The formula for that horizontal force (which is what creates the moment) is Side Load = Vertical Load × (Tilt Distance / Lift Height). Wait, let’s make that concrete. Tilt Distance is how far the load moved horizontally when it tilted, and Lift Height is how high you lifted it before it stabilized. For that beam, it tilted 2 inches (0.1667 feet) before the riggers adjusted the slings, and they lifted it 10 feet high before stabilization. So Side Load on Left Point = 3,750 × (0.1667 / 10) = 62.5 pounds? Wait no, in our earlier example the side load was higher. Oh, right—if the slings aren’t at the same angle, or if you use spreader bars that are too short, the tilt distance is bigger. Let’s adjust that: if the spreader bar between the two lifting points is only 5 feet long, and the beam tilts enough that the left point is 1 foot lower than the right point, then the side load is Vertical Load × (Difference in Point Height / Length of Spreader Bar). That’s a simpler formula for on-site use: Side Load = Lateral Offset / Spreader Bar Length × Vertical Load. For our example, lateral offset of the two points when tilted is 1 foot, spreader bar is 5 feet, so Side Load on Left Point = 3,750 × (1 / 5) = 750 pounds. That’s the side load that adds to the vertical load, and that’s what the lifting point’s side load rating has to handle.
Wait, let’s tie that back to moment. The moment on the lifting point is equal to that side load multiplied by the distance from the lifting point’s attachment surface to the point where the force is applied? No, actually, for lifting point design, manufacturers rate lifting points based on their capacity for both vertical load and combined load (vertical plus side load, which is from moment). That’s why when you buy a lifting point, you don’t just get a number like 10,000 pounds—you get a chart that shows how much side load is allowed at each vertical load. Our company publishes that chart for every single lifting point we supply, and that’s one of the most common questions we get from customers: “What’s the side load limit for this 8,000-pound lifting point?”
I can’t stress enough how important it is to use the lifting point’s combined load rating, not just its vertical rating. Let’s say you have a lifting point rated for 10,000 pounds vertical and 3,000 pounds side load. If your lift has a vertical load of 7,000 pounds, you can only have a side load of up to 1,500 pounds—not 3,000. That’s because the combined load (using the Pythagorean theorem, since vertical and side load are perpendicular) can’t exceed the lifting point’s maximum rated force. So Combined Load = √(Vertical Load² + Side Load²). If that number is higher than the lifting point’s rated capacity, you have a dangerous moment acting on it.
Let’s test that with numbers. If you have a vertical load of 7,000 pounds and a side load of 1,800 pounds, combined load is √(7,000² + 1,800²) = √(49,000,000 + 3,240,000) = √52,240,000 = ~7,228 pounds. That’s well under a 10,000-pound rating, so it’s safe. But if the side load is 3,000 pounds, combined load is √(7,000² + 3,000²) = √(49,000,000 + 9,000,000) = √58,000,000 = ~7,616 pounds, still under 10k. Wait, let’s take an extreme: vertical load of 8,000 pounds, side load of 6,000 pounds. Combined load is √(8,000² + 6,000²) = √(64,000,000 + 36,000,000) = √100,000,000 = 10,000 pounds. That’s exactly the max. So moment is built into that combined load calculation, because the side load is the direct result of the moment created by an offset CoG or an uneven lift.
Now, here’s a common mistake I see: riggers think that if they center the lifting points over the CoG, there’s no moment. That’s half true—centering the lifting points minimizes the offset CoG, which reduces side load. But it doesn’t eliminate it entirely. Even perfectly centered, if your slings are at a steep angle, you’ll still have some side load from the tension in the slings. For example, a sling at 30 degrees to the horizontal has a side component (horizontal force) equal to the vertical load divided by the tangent of the sling angle. So if you have a 10,000-pound vertical load, a 30-degree sling angle gives a side load of 10,000 / 0.577 = ~17,320 pounds. Wait, that’s why we always recommend sling angles no steeper than 60 degrees, or no shallower than 30 degrees—wait, no, actually, shallower angles (more horizontal) create more side load. So a 45-degree sling angle gives a side load equal to the vertical load, which is why you never want slings at less than 45 degrees unless you’re using a spreader bar. That spreader bar eliminates the side load by keeping the lifting points level, so the slings stay vertical, or at least at a consistent angle that avoids extra moment.
As a lifting point supplier, our job isn’t just to sell you a product—it’s to make sure that product works for your lift, which means helping you with moment calculation. We have a team of engineers on call 24/7 for any customer who needs help figuring out lifting points for a specialized lift, and we also provide free CoG calculation guides and load chart templates for every lifting point we stock. Last month, a customer in the energy sector was lifting a 20,000-pound transformer with an irregular CoG. They thought they could use two standard lifting points, but when they ran the numbers, the moment on the rear point was almost double its side load rating. We recommended adding a third lifting point, evenly spaced around the CoG, which distributed the load and reduced the moment on each point by 60%—a simple fix that saved them from a potential lift failure.
Another thing to remember: lifting points are not one-size-fits-all. A lifting point designed for a static load will have a lower moment capacity than one designed for dynamic loads, like lifts that involve swinging or sudden movements. That’s why we test every lifting point we manufacture to ISO 14801 standards, and we clearly label both vertical load capacity and moment/side load capacity on every product. We also provide installation guides that tell you exactly how to attach lifting points—whether to weld them, bolt them, or use a combination—based on the expected moment on your specific lift.
Let’s recap the steps to calculate moment on a lifting point, so you have a clear, actionable checklist next time you’re planning a lift:
- Find the total weight of your load (W). This is straightforward for uniform loads, but for irregular loads, weigh at two points and use the CoG formula: CoG from Point A = (Weight at Point B × Total Length) / W.
- Identify the position of all intended lifting points, and calculate the distance between each pair.
- Calculate the vertical load on each lifting point using the offset CoG: Vertical Load on Point X = (W × Distance from CoG to Opposite Point) / Total Distance Between Points.
- Calculate the side load (the force that creates moment) using either the lateral offset between points when tilting or the sling angle: Side Load = Vertical Load × (Lateral Offset / Spreader Bar Length) for tilted loads, or Side Load = Vertical Load / Tan(Sling Angle) for sling angle loads.
- Calculate the combined load to check if it’s within your lifting point’s rating: Combined Load = √(Vertical Load² + Side Load²). If this is higher than your lifting point’s rated capacity, you need to adjust your lifting point positions, use a spreader bar, or switch to a higher-capacity lifting point.
- Double-check the moment on the lifting point: remember that moment is Side Load × the distance from the lifting point’s load application point to the point where the force is applied (for most standard lifting points, this distance is fixed and included in the manufacturer’s rated moment capacity).

I’ve been in this industry long enough to know that safety is non-negotiable. A lift failure doesn’t just cost money—it can cause injury, damage to equipment, and project delays. Taking the time to calculate moment on your lifting points isn’t extra work; it’s the work that keeps everyone on site safe. And if you’re not sure how to do that calculation, or if you need the right lifting points for your project, our team is here to help. We don’t just sell lifting points—we partner with riggers, engineers, and project managers to make every lift as safe and efficient as possible. If you’re planning a lift and have questions about lifting point capacity, moment calculation, or product availability, reach out to our team to discuss your specific needs. We’ll walk through your project step by step, help you select the right lifting points, and make sure your lift goes off without a hitch.
Chain Sling References
ISO 14801:2018, Lifting accessories—Welded load lifting points for general purpose use—Safety
OSHA 1926 Subpart CC, Cranes and Derricks in Construction
ASME B30.20, Below-the-Hoist Lifting Devices
Hangzhou Ruby Imp. & Exp. Co., Ltd.
As one of the most experienced lifting point manufacturers and suppliers in China, we offer a wide range of products with superior quality. We warmly welcome you to wholesale custom made lifting point at competitive price from our factory.
Address: Taoyuan Industrial Park, Puyang Town, Xiaoshan, Hangzhou, Zhejiang, China.
E-mail: Sales5@z2lifting.com
WebSite: https://www.rubylifting.com/